Key informations about our projects
Investment schedule
The commissioning of the first stage of the project, i.e. Baltica 3 with a capacity of up to 1045.5 MW, is planned for 2026. The next stage, i.e. Baltica 2 with a capacity of up to 1,497 MW, is to be commissioned by 2027. Both of these stages of the Baltica OWF have location decisions (PSzW), environmental decisions for the offshore part, contracts for connection to the transmission network with the operator, and were also granted the right to a contract for difference (CfD). In 2022, we expect to receive an environmental decision for the onshore transmission part. We will also work on obtaining construction permits, which will enable us to make the final investment decision. We plan to put the Baltica 1 project into operation after 2030.